Posted on: March 9, 2018

W. Shady Shores Road Repair

Site Map - W Shady Shores Rd Construction (002).jpg

Dear Resident:

The contractor, Anderson Asphalt and Paving will begin construction on Site 1 of this project on March 10, 2018 (a map is included on the reverse side of this document for reference). The schedule of work to be completed is as follows:

  • 3/10/18 – 3/12/18 Excavation
  • 3/12/18 – 3/13/18 Place Portland Cement for subgrade stabilization
  • 3/14/18 – 3/15-18 Microcrack the subgrade
  • 3/16/18 Prime coat the subgrade
  • 3/17/18 and 3/19/18 Asphalt paving

There may be delays or changes in the schedule due to weather or other unforeseen circumstances.

Work will be done between the hours of 7 am to 6 pm.

Barricades will be in place at various locations and the road will be closed to through traffic.  Residents will have access to their homes at this time.

Solid Waste and Recycling will be picked up as usual.  Residents should place their carts outside at the usual time and place on Wednesday morning.  If the section of roadway where you live is barricaded so that the trucks cannot reach you the contractor will make sure that your cans are emptied and replaced at your driveway.  RESIDENTS ARE ENCOURAGED TO MARK THEIR CANS WITH THEIR ADDRESS SO THAT IT CAN BE CLEARLY SEEN.  There will be no bulk pick up during this time.

Mail will be delivered as scheduled.

If you have any questions, please contact Wendy Withers at 940-498.0044,

Thank you,